The Barn is a 60ft x 60ft metal building. This building was designed as a monitor building, matching other building styles in the neighborhood. Despite the monitor style, there are no internal columns and is a clear span construction.

Time-lapse of the Barn construction
Thickened Edge Slab August 28, 2024 – The barn’s foundation was engineered as a monolithic slab with a thickened edge. Tor checking the plans Electrical stubbed out prior to the pour Data and power conduits Plumbing stubbed out Gravel prep for the slab. The weather is hot, so the decision has been made to pour the slab in two sections over 2… …
Drainage September 25, 2024 – The roof water is collected into a 52ft dispersion trench Catchment basin Clean out Ready for inspection Covered after inspection …
Main Frame Erected October 11, 2024 – A giant erector set We uncovered Fluffy while moving the posts …
PSE Hookup May 22, 2025 – Once the permit was issued, PSE hooked up power to the barn. PSE installed overhead power to the strike point on the barn Let there be light! Powered garage doors are also amazing …
Spray Foam June 16, 2025 – The barn was completely emptied to spray foam 2 inches of closed cell foam. …